This project is going to improve the effectiveness and
energy efficiency of lighting in UNSW buildings.
Specialist lighting contractors will be improving the effectiveness and efficiency of the lighting at UNSW. This may include some or all of the following measures:
The table below shows the work that will be conducted as part of this project.
| Morven Brown Building (level 3) - completed |
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 301 |

|
|
|
|

|
| 301A |

|
|
|
|

|
| 302 |

|
|
|
|

|
| 303 |

|
|
|
|

|
| 304 |

|

|
|
|
|
| 304A |

|

|
|
|
|
| 304B |

|

|
|
|
|
| 304C |

|

|
|
|
|
| 305 |

|

|
|
|
|
| 306 |

|

|
|
|
|
| 307 |

|

|
|
|
|
| 314 |

|

|
|
|
|
| 315 |

|

|
|
|
|
| 317 |

|

|
|
|
|
| 318 |

|

|
|
|
|
| 319 |

|

|
|
|
|
| 320 |

|

|
|
|
|
| 321 |

|

|
|
|
|
| 322 |

|

|
|
|
|
| 323 |

|

|
|
|
|
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 324 |

|

|
|
|
|
| 325 |

|

|
|
|
|
| 326 |

|

|
|
|
|
| 328 |

|

|
|
|
|
| 329 |

|

|
|
|
|
| 330 |

|

|
|
|
|
| 331 |

|
|
|
|

|
| 332/334 |

|

|
|
|
|
| 333 |

|

|
|
|
|
| 335 |

|

|
|
|
|
| 336 |

|

|
|
|
|
| 337 |

|

|
|
|
|
| 338 |

|

|
|
|
|
| 339/341 |

|

|
|
|
|
| 340 |

|

|
|
|
|
| 342 |

|

|
|
|
|
| 343 |

|

|
|
|
|
| 344 |

|
|
|
|

|
| 345 |

|

|
|
|
|
| 346 |

|

|
|
|
|
| 347 |

|
|
|
|

|
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 348 |

|

|
|
|
|
| 349 |

|

|
|
|
|
| 350 |

|

|
|
|
|
| 350A |

|

|
|
|
|
| 351 |

|

|
|
|
|
| 351A |

|

|
|
|
|
| 352 |

|

|
|
|
|
| 353 |

|

|
|
|
|
| 354 |

|
|
|
|

|
| 355 |

|

|
|
|
|
| 358 |

|

|
|
|
|
| 359 |

|

|
|
|
|
| 360 |

|

|
|
|
|
| 361 |

|

|
|
|
|
| 362 |

|

|
|
|
|
| 363 |

|

|
|
|
|
| 364 |

|

|
|
|
|
| 365 |

|

|
|
|
|
| 366 |

|

|
|
|
|
| 367 |

|

|
|
|
|
| 368 |

|

|
|
|
|
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 369 |

|

|
|
|
|
| 370 |

|

|
|
|
|
| 371 |
|
|
|
|

|
| 372 |

|

|
|
|
|
| Corridors |

|
|
|
|

|
| Toilets |

|
|
|
|

|
| Totals |

|

|
|
|
|
| Electrical Engineering Building (levels LG and 2) - completed |
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| LG10 |

|
|

|
|

|
| LG11 |

|
|
|
|

|
| LG12 |

|
|
|
|

|
| LG13 |

|
|
|
|

|
| LG14 |

|
|
|
|

|
| LG15 |

|
|
|
|

|
| LG17 |

|
|
|
|

|
| 201A |

|
|
|
|

|
| 201B |

|
|
|
|

|
| 201C |

|
|
|
|

|
| 202A |

|
|
|
|

|
| 202B |

|
|
|
|

|
| 202C |

|
|
|
|

|
| 202D |

|
|
|
|

|
| 202E |

|
|
|
|

|
| 203 |

|

|
|
|
|
| 204 |

|

|
|
|
|
| 205 |

|

|
|
|
|
| 206 |

|

|
|
|
|
| 207 |

|

|
|
|
|
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 208 |

|

|
|
|
|
| 209 |

|

|
|
|
|
| 210A |

|
|
|
|

|
| 211 |

|
|
|
|

|
| 211A |

|
|
|
|

|
| 212 |

|
|
|
|

|
| 213 |

|
|
|
|

|
| 213A |

|
|
|
|

|
| 213B |

|
|
|
|

|
| 214 |

|
|
|
|

|
| 215 |

|
|
|
|

|
| 215B |

|
|
|
|

|
| 216 |

|

|
|
|
|
| 217 |

|

|
|
|
|
| 223 |

|

|
|
|
|
| 227 |

|
|
|
|

|
| 227A |

|
|
|
|

|
| 228A |

|

|
|
|
|
| 231/232 |

|
|
|
|

|
| 233 |

|

|
|
|
|
| 234A |

|

|
|
|
|
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 234B |

|

|
|
|
|
| 235 |

|

|
|
|
|
| 236 |

|

|
|
|
|
| 237A |

|

|
|
|
|
| 237B |

|

|
|
|
|
| 238 |

|
|
|
|

|
| 239 |

|
|
|
|

|
| 240A |

|
|
|
|

|
| 240B |

|
|
|
|

|
| 240C |

|
|
|
|

|
| 240D |

|
|
|
|

|
| 241A |

|
|
|
|

|
| 241 |

|
|
|
|

|
| 242 |

|
|
|
|

|
| 243 |

|
|
|
|

|
| 244 |

|
|
|
|

|
| Corridors |

|
|
|
|

|
| Toilets |

|
|
|
|

|
| Mechanical Engineering Building (levels 2 and 3) - completed |
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 201 |

|

|
|
|
|
| 204 |

|

|
|
|
|
| 205 |

|
|
|
|

|
| 205A |

|
|
|
|

|
| 206 |

|

|
|
|
|
| 207 |

|

|
|
|
|
| 208 |

|

|
|
|
|
| 209 |

|

|
|
|
|
| 210 |

|

|
|
|
|
| 211 |

|

|
|
|
|
| 212 |

|

|
|
|
|
| 213 |

|

|
|
|
|
| 214 |

|

|
|
|
|
| 215 |

|

|
|
|
|
| 216 |

|

|
|
|
|
| 217 |

|

|
|
|
|
| 218 |

|

|
|
|
|
| 219 |

|

|
|
|
|
| 302 |
|

|
|
|
|
| 305 |

|

|
|
|
|
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 307 |

|

|
|
|
|
| 308 |

|

|
|
|
|
| 309 |

|

|
|
|
|
| 310 |

|

|
|
|
|
| 311 |

|

|
|
|
|
| 312 |

|

|
|
|
|
| 313 |

|

|
|
|
|
| 314 |

|

|
|
|
|
| 315 |

|

|
|
|
|
| 316 |

|

|
|
|
|
| 317 |

|

|
|
|
|
| 318 |

|

|
|
|
|
| 319 |

|

|
|
|
|
| 320 |

|

|
|
|
|
| Corridors |

|

|
|
|
|
| Toilets |

|

|
|
|
|
| Civil Engineering Building (levels 3 and 4) - Work started late January |
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 301 |

|

|
|
|
|
| 301A |

|

|
|
|
|
| 301B |

|

|
|
|
|
| 301C |

|

|
|
|
|
| 302 |

|

|
|
|
|
| 303 |

|

|
|
|
|
| 304 |

|

|
|
|
|
| 306 |

|

|
|
|
|
| 307 |

|

|
|
|
|
| 308 |

|

|
|
|
|
| 309 |

|

|
|
|
|
| 310 |

|

|
|
|
|
| 310A |

|

|
|
|
|
| 310B |

|

|
|
|
|
| 310C |

|

|
|
|
|
| 310D |

|

|
|
|
|
| 311 |

|

|
|
|
|
| 312 |

|

|
|
|
|
| 313 |

|

|
|
|
|
| 314 |

|

|
|
|
|
| Room Number |
Movement Detector |
New Light Fittings |
Extra Switches |
Improved Reflectors |
New Lamps or Diffusers |
| 315 |

|

|
|
|
|
| 316 |

|

|
|
|
|
| 317 |

|

|
|
|
|
| 318 |

|

|
|
|
|
| 401 |

|

|
|
|
|
| 402 |

|

|
|
|
|
| 403 |

|

|
|
|
|
| 404 |

|

|
|
|
|
| 405 |

|

|
|
|
|
| 406 |

|

|
|
|
|
| 407 |

|

|
|
|
|
| 408/409 |

|

|
|
|
|
| 410 |

|

|
|
|
|
| 411 |

|

|
|
|
|
| 412 |

|

|
|
|
|
| 413 |

|

|
|
|
|
| 414 |

|

|
|
|
|
| 415 |

|

|
|
|
|
| Toilets |

|

|
|
|
|
| Corridors |

|

|
|
|
|